Work progresses on Roche de Boeuf Interurban Bridge

Perched on a stone wall on Farnsworth Metroparks’ Roche de Bout overlook last week, Maumee residents Brian and Jane Tomko watched as Kokosing operators carefully removed pieces of the Roche de Boeuf Interurban bridge and dump trucks hauled away the debris.

Nearly every day, the overlook has visitors arriving by car, bike and foot, to watch the removal of the 118-year-old bridge’s spandrel walls and filler to expose the 12 concrete arches.

Brian and Jane Tomko, who live near Side Cut Metropark, came upriver to watch the work on the Roche de Boeuf Interurban Bridge last week. The Roche de Bout Overlook at Farnsworth Metropark is a popular viewing area for those watching the progress. (AWFP photo by Karen Gerhardinger)

“We’re over halfway through. It seems to be a solid, strong structure,” said Waterville Mayor Tim Pedro. “We’ve got professionals doing the job.”

The city agreed to purchase the bridge from the state earlier this year, just as a one-year pause on demolition was set to expire, after information from historic bridge engineer Bill Vermes and concrete expert John Pautz II confirmed that the arches and piers could be saved if the spandrel walls holding in the earthen fill could be removed. Save The Bridge Association (STBA) and the city announced plans to use the remaining arches for Phase 2: installing a pedestrian and bike bridge over the top once funds are raised for the project.

For Kokosing, which was contracted by Ohio Department of Transportation (ODOT) to initially demolish the bridge in its entirety, the pivot to partial demolition has come with its challenges and surprises, said Craig Wing, senior area manager for Kokosing.

“Trying to save something this old, and in this condition, is unique,” Wing said earlier this month, as he looked out onto the causeway on the Wood County side. “We told ODOT that this was going to be a bit of a science project, that it was going to take a few iterations to find out what was going to work. We’re probably on Plan E or F at this point.”

Kokosing crews were removing spandrel walls and debris from the Roche de Boeuf Interurban Bridge last week. (AWFP photo by Karen Gerhardinger)

Using excavators with hoe ram attachments that are like little hydraulic hammers, Kokosing operators have been working on perfecting methods for removing the backfill and the spandrel walls without damaging the arches. It’s not a typical job, but Wing said he had several experienced operators who readily volunteered to work on this historic project. 

“A lot of times those guys have the best ideas in terms of what is going to work. They’re the guys in the seats, and they know what it looks like and feels like. It’s been a lot of trial and error, figuring out what to do. Everybody has played a part in that,” Wing adding, “A lot of it is figuring out the sequencing.”

Pointing up to the arches, Wing explained that initially crews planned to hydro-excavate some of the dirt first, using water to open up the top to get a better look at the joints. But after removing the top six to eight inches of dirt, they ran into an unexpected surprise: a layer of asphalt that had been put in place when the structure was briefly used as a roadway bridge in the 1940s after the downstream Waterville bridge was heavily damaged in an accident.

Crews are removing the spandrel walls and the dirt filler on the bridge, while dealing with tree roots and rebar in the process. (AWFP photo by Karen Gerhardinger)

Crews also discovered more reinforcing in the bridge than they originally thought, especially between the joints and spandrel walls. Sketches from a book on bridge designer Daniel Luten helped some, but there were no plan sheets to refer to, he said.

“As we entered this process, there were no guarantees that we were going to be able to save the arch. At any time, we could hit this thing, or not even hit it – we could just look at it wrong – and it could crack,” Wing said. “We are doing our best.”

Among the other surprises were hanging tree roots and rebar, and having chunks of concrete falling when they least expected it. That’s why Wing has told crew members walking around on the causeway to have their heads “on a swivel” and be focused and aware. He doesn’t want the ground people walking around when operators are working on a span in case it impacts another area nearby. 

Last week, the team was working on the Wood County side, but eventually the causeway will be flipped back to the Waterville side to do removal of the lower spandrel walls. Once all the work is done and the rocks are removed from the river, the final phase is to plant trees and bushes on the abutments. Crews cannot work in the river between April 1 and Aug. 1 because of fish spawning. 

“Right now, we’re in pretty good shape. I’d like to say we’ll beat the April date by several months. We’ll be in the river on the causeway until the rocks come out. Hopefully it’s not all winter,” Wing said.

Weather has also had some impacts. In September, the work took a week-long pause after heavy rains caused fast-moving currents to open up two spans of the causeway. When water is on the causeway, equipment and people are not safe.

Graffiti adorns the underside of span 12. (AWFP photo by Karen Gerhardinger)

Throughout the work, the Roche de Boeuf Island, which was the site of Native American gatherings in the 1700s, is protected with rubber mats to protect it from falling rock.

“We understand the history and significance of the rock,” Wing said of the island, which was blasted down when the bridge was built.

Despite the challenges, the operators have really enjoyed working on the river, where they see herons, eagles and other wildlife, as well as spectators. The operators understand the sensitivity around the project when it comes to public opinion, and don’t want to be named, Wing said. 

A Monclova Township resident, Wing has heard a lot of the comments himself, and jokes that despite his bachelor’s degree in civil engineering, master’s degree in construction management and 36 years of experience, he hears his fair share of criticism.

“I’ve had a lot of people trying to explain in the last few months what I don’t know,” he said.

He’s also seen the AI-generated renderings on what the bridge will look like when it’s finished, and he calls them misleading.

“Get that out of your head,” he said of the renderings. “That’s not what it’s going to look like. In the rendering, everything looks nice and fresh. It’s going to look like half the bridge was removed…with jagged edges.”

Wing also cautioned against climbing on or under the bridge, which he said is not safe. He gets photo evidence of this happening regularly, despite signs warning people to stay away.

Save the Bridge Association member Rex Childers and Vermes have been on site, as they work on planning for the next phase. Vermes, who has experience saving historic bridges, has been measuring and recording information on the pilasters – which stand above the piers but are being removed in the project. 

“We’re measuring details so we can replicate the features when the bridge gets full rehabilitation,” he said. “We will be losing all of this information once the walls are down.”

The people that poured the concrete on the bridge were artisans, Childers remarked, noting that the artistic detail on these pilasters are work replicating.

With the work more than half done, Childers said he’s excited about how the city and STBA can work together to raise funds through grants, donations and partnerships to prepare engineering for its future use.

“The bridge is standing. It’s going to stand. Now it’s time to pivot to grant writing and fundraising. There will be a bridge. Get excited for it,” he said.

An excavator sits idle on the causeway at the end of the day. (AWFP photo by Karen Gerhardinger)

Karen Gerhardinger
Karen Gerhardinger
Karen Gerhardinger is a freelance journalist with a passion for sharing the stories of communities - including schools, local government and nonprofit organizations. An Anthony Wayne High School graduate, Karen earned a bachelor's degree in journalism from the University of Texas at Arlington. Her career has included positions with The Fort Worth Star-Telegram, The Columbus Dispatch and The Mirror Newspaper. To share story ideas, email [email protected].

Related Articles

 

Stay Connected

6,978FansLike
1,921FollowersFollow
8,952FollowersFollow
98SubscribersSubscribe

Latest Articles