TOLEDO – Last week, Toledo City Council was dominated by a decision over a Flock resolution, but what shouldn’t be lost in that political contention are the grants the city received.
“I just want to acknowledge that we voted to bring in $21.7 million in grants today,” said Nick Komives, Toledo City Council member at-large, during his closing remarks. “So congrats to anybody who’s been involved in those.”
The largest of these grants was for $19,510,645, awarded through the Federal Highway Administration (FHA) and the Ohio Department of Transportation (ODOT).
OBBBA dee, life goes on
Originally this grant was awarded to the city in March 2024 for reshaping the Front Street & Main Street intersection on the east side of Toledo, deemed the Front and Main Corridor Modernization project, but was delayed by the One Big Beautiful Bill Act (OBBBA).
During the summer of 2025, Toledo Mayor Wade Kapszukiewicz, along with other city officials and representatives, pleaded with the public to reach out to Ohio Senators Jon Husted and Bernie Moreno, to try to save the funding, which found its way onto the chopping block through cuts in the OBBBA.
It was/is believed that the $28.5 million grant through Department of Transportation’s Reconnecting Communities and Neighborhoods Grant, which was a subsection of the Neighborhood Access and Equity Grant Program, was cut due to language surrounding the grant, not due to the substance of the project.

Theresa Gadus, council member for the area, District 3, emphasized the high frequency of crashes at the intersection, as well as the intersection’s proximity to schools.
In 2025, Simon Nyi said that “this corridor is less than a mile long, yet in the past 10 years, traffic crashes here have tragically taken five lives and left 34 more with life-changing injuries.” Nyi was the lead in securing the grant as the grants commissioner for the City of Toledo.
Almost as a bad omen, a few months later on Oct. 6, 2025, a man drove his vehicle into the Wendy’s at the intersection, causing structural damage to the building.

Regained footing
The mayor and Nyi were concerned about losing momentum on the project, and were worried this revoked funding could set the project back a decade or so, but a little over a year later, Nyi presented the project grant to council during their agenda review on Oct. 13.
“This project includes…a comprehensive improvement of Front Street from Oak Street to the Interstate 280 and Main Street from the Animal King Bridge to Nevada, includes resurfacing, medians, street trees, several lane intersection reconfigurations and pedestrian improvements throughout the corridor,” Nyi said. “This is the same project that we previously received funding for, with a couple of changes.”
Early in the planning phase, the project included a roundabout at Main Street and Starr Avenue, which Nyi said they had revised due to community feedback. “Let me say the removal of the roundabout happened quite some time ago, before the rescissions,” he said.
“The other change was actually an addition to the project,” which were horizontal infrastructure additions, to help with bus rapid transit (BRT) for TARTA.
Noticing the difference in the grants ($28 to $19 million), At-Large Councilman George Sarantou inquired as to why there was roughly a difference of $9-10 million dollars between them.
Luckily, not all $28 million was cut. “We were able to get some of the federal design funding obligated,” Nyi said. Eliminating the roundabout did save some costs, but when the project started, Nyi said it was at the conceptual stage. “Now it’s at 80 percent completion” of the design stage, he said.
“We have much more accurate cost estimates and better understanding of how much materials we need and things of that nature.”

Forward progress
Nyi was happy to announce the final design for the project was underway, construction will begin in summer of 2027, and the corridor should be completed sometime by the end of 2028.
“I just want to thank everyone,” Gadus said, glad to have the needed traffic infrastructure updated.
At-Large Member Erin Kramer raised concerns about traffic infrastructure during construction, and Nyi said Stephanie Bartlett, the commissioner of traffic management, had a traffic plan forthcoming.
Ultimately, Nyi, who secured the original grant and a second round of grants, had some of the most heartfelt comments on the east side plan.
“Our understanding is that a big part of the reason that the funds were rescinded was that that program happened to include the word ‘equity,’” Nyi said.
“When you apply for federal grants, of course, you have to speak to the priorities of the administration at that time,” he said. “I think what we were able to demonstrate with our application to the build program this time, with a different set of priorities, is that the benefits of this project, in terms of safety, connectivity, mobility, and economic development, are the kind of fundamental transportation infrastructure improvements that are going to benefit the neighborhood and benefit the community, regardless of what sort of language you use to to make the sales pitch, so to speak.”
“I’m just happy that we are able to deliver this project that I think is going to be really impactful for the residents of the east side. At the end of the day, this is a project about safety, mobility, and economic development…and I’m happy to see it becoming reality,” Nyi said. “We’re ready to deliver this project and excited to see it move forward.”